Course:                                    ENT 6A6: Project Management for Enterprise

Assessment:                            Assessment Two: Creating a Project Plan

Report Word Count:                 2,500 words maximum

TMM:                                        60%

Summative Submission:          Project Plan in MS Project

Individual Report in MS Word/PDF

Module Leader:                       

This is an individual assessment that requires students to develop a project plan using MS-Project and submit an individual report. In the report you will describe the key methods used and steps taken to create your project plan (include screen shots to evidence your work). Additionally, you are expected to use a range of academic sources to substantiate explanations of the key techniques used. You will be expected to reference additional sources beyond the core text and class materials.

 

The two components to be assessed are:

 

  • Report: 2,500 created in MS-Word or PDF
  • Project Plan created in MS-Project

After considering your initial scoping and planning documentation from assessment one, the Business Owner of Amber cars has contacted you to run the project for the company. In light of the considerations presented from the initial scoping and planning documentation, the Business Owner has made the following adjustments to the project scope:

 

Project: Amber Cars Website Development Project

Start Date: 9th April 2018

Required End Date: 58 working days from the start date

Budget: £13,000

Quality Specifications: Website design confirms to established guidelines as well as meeting requirements specified in the Data Protection Act (UK Legislation 1998).

 

You will need to create a project plan starting from the 9th April 2018. Project task durations and costs allocated to each task can be found in table 1. You are required to consider the resources needed to undertake the project, how much you will spend on material and work resources and to ensure the project is planned to complete within time and on budget.

 

 

The report will enable you to demonstrate your individual reflections and understandings on the criticality of project planning and monitoring and control. There are four key sections to the report, which are:

 

Section One: Introduction

Section Two: Planning (see Project Plan section)

Section Three: Monitoring and Control (see Project Plan section)

Section Four: Evaluation (refer to Marking Scheme)

 

You must include a reference page at the back – remember to cite academic sources. The work must also include a title page (with student name and number clearly specified) and a content page.

 

 

In the Planning and Monitoring and Control sections of your report, you need to evidence the following using MS-Project:

 

Planning Monitoring and Control
·         Set the project start date

·         Enter all project tasks, durations and dependencies

·         Enter all project phases

·         Entering work resources

·         Entering material resources

·         Assigning resources

·         Changing the working time of a resource

·         Dealing with resource overallocation

·         Adding milestone tasks

·         Adding a deadline task

·         Adding recurring tasks

·         Adding a task constraint

·         Saving a baseline

·         Entering completed tasks

·         Entering 75% completed tasks

·         Entering 50% completed tasks

·         Entering 33% completed tasks

·         Entering task notes

·         Entering resource notes

·         Missing deadline date

·         Task variance

·         Cost variance

 

 

 

 

Submission requirements for this assessment are outlined in the table below:

 

Submission Item Information Submitted Via Submission date
Project Plan

An electronic copy of the project plan in MS-Project

 

The project plan should feature the elements indicated on the marking scheme. Blackboard Sunday 29th April by 11.59pm.
Individual Report

An electronic copy of the report in MS-Word or PDF format

 

The report should be formatted as follows: Arial, size 12, single line spacing. Include a contents page and a title page (with your name and student number) Blackboard Sunday 29th April by 11.59pm.

 

 

Plagiarism includes submitting work that has been written by someone else and copying passages from other sources without references. Plagiarism is easy to detect and will be acted upon. The Academic Misconduct procedures at Regent’s University London will be followed in cases of plagiarism.

 

 

Table 1: Project Activity Information

 

Activity

ID

Phase Number Phase Description Activity Name Predecessor

 

Duration

E (D)=

Cost
A One Requirements Analysis Elicit client needs 2 £420
B One Requirements Analysis Target audience analysis A 2 £400
C One Requirements Analysis Gain server access 2 £200
D One Requirements Analysis Gain required resources A 3 £200
E One Requirements Analysis Requirements specification B, D 4 £400
F One Requirements Analysis Gain approval E 2 £100
G Two Prototyping Create prototype C, F 3 £200
H Two Prototyping Approval of prototype G 2 £175
I Two Prototyping Test prototype H 1 £250
J Two Prototyping Amend prototype I 2 £100
K Two Prototyping Gain approval from J 2 £130
L Three Development Create coding templates K 4 £1,000
M Three Development Create HTML and CSS documents L 8 £1,000
N Three Development Develop interactive components M 3 £1,500
O Three Development Add content K, L 4 £2,000
P Three Development Verify site links O 2 £200
Q Three Development Verify functionality P, N 2 £100
R Three Development Gain approval from client Q 2 £100
S Four Testing Cross browser testing R 3 £200
T Four Testing Error testing R 2 £200
U Four Testing User group testing R 4 £1,000
V Four Testing Amendments arising from testing S, T ,U 5 £1,800
W Four Testing Gain approval from client V 2 £240
X Five Training Provide client with training W 3 £300
Y Six Project Close Connect website to database W 2 £200
Z Six Project Close Launch website X, Y 2 £150
ZA Six Project Close Project Review and Close  Z 2 £150

 

 

 

 

Section 1 INTRODUCTION 5% Poss Act
  Introduction to the project aims and objectives 5
 
Section 2 PLANNING 35%    
  Set project start date 1
  Entering all project tasks, durations and predecessors 3
  Enter all phases 2
  Entering work resources 4
  Entering material resources 4
  Assigning resources 4
  Changing the working time of a resource 3
  Dealing with resource overallocation 4
  Adding milestone tasks 3
  Adding a deadline task 3
  Adding recurring tasks 1
  Adding a task constraint 2
  Saving the baseline 1
     
Section 3 MONITORING AND CONTROL 20%    
  Tasks completed entered 2
  Some tasks only partly completed (75%, 50%, 33%) 5
  Task Notes entered 2
  Resource notes entered 2
  Missing deadline date 1
  Task variance 4
  Cost variance 4
 
Section 4 CRITICAL EVALUATION 10%
  Critical reflection on achieving the project’s aim and objectives 2
  Critical evaluation on techniques beneficial to overall planning 3
  Critical evaluation lessons learned? 3
  Recommendations for future similar projects regarding the planning activities 2
 
QUALITY OF WORK 30%    
  Quality of report and referencing 5
  Explanations of key techniques and critical review 25
  Total 100  

 